Please ensure Javascript is enabled for purposes of website accessibility
Notice 10-19-2026 : Municipal Complex Project: Learn more at Fire Dept. Open House on 10/24 ( 10am-1pm), Police Dept. Open House on 10/31 (9am-1pm), Town Hall M-F (during regular business hours), Public Forum on 10/29 (7:00 pm) Thayer Homestead

Paving/Sidewalk Schedule 8/25-8/29

Final Paving & Roadwork Schedule

  • Monday, August 25: Final paving begins on Laurelwood Lane, Stephanie Drive, and Kimberly Drive.

  • Tuesday, August 26: Crews will complete paving on Diane Drive, Colonial Road, Wildebrook Road, First Colony Drive, and Canal Street.

The sidewalk contractor will also be on-site on Tuesday, August 26, to finish paving their portion of Laurelwood Lane. Loaming will follow, with final work on Laurelwood wrapping up by Wednesday, August 27. Crews will then move into the neighborhood to complete paving and loaming on the final three sidewalks.

Additionally, long line painting will begin Monday night, August 25, taking place during overnight hours and into the early morning.