Road Work - Milling (starting 5/15)

Posted on: May 14, 2024 - 9:34am

Crews will be going throughout town starting on May 15. Milling will start on Oakland Street (between Main St. and Oakland Well Road). From there, crews will move on to Grapevine Way and Hillside Court. Once complete, they will move on to Evergreen/Elm, Royal Heights, Wellington, Norfolk, Lincoln, High, Sherwood, and Stanley. Milling will last 3-5 days, dependent on weather. All milling operations will be completed with traffic.

Depending on the weather, crews are slated to start laying a topcoat of pavement on Monday, May 20, on the above roads, following the same order of operations.