Route 109 update for the week of September 11, 2017

The contractor will continue to install electrical conduit along Main Street for the traffic lights and street lights. They will also be prepping for pavement from 159 Main Street to Temple Street on Monday, and paving that section on Tuesday and Wednesday. 

After the paving they will start reclaiming the next section heading east on Main Street.