Big construction updates are coming to Summer Street starting next week. Please review the schedule below so you can plan your commutes and nighttime travel:
🌙 Nighttime Milling (Mon, July 6 – Fri, July 10 - subcontractor may be able to complete the work sooner):
-
Work runs from 8:00 PM to 5:00 AM each night.
-
Crews will start at the Main St. side of Summer St.
🏗️ Structure Adjustments (Tuesday):
-
Crews will be on-site adjusting structures starting from the Main St. end to prepare the road for paving.
🚧 Paving & Road Closure (Thursday, July 9):
-
Paving begins from Main St.
-
ROAD CLOSURE: Summer St. will be temporarily closed between Main St. and Milford St. so crews can pave safely.
Police details and clear signage will be on-site to direct traffic. Local access will be fully maintained for residents, businesses, and the day care. Thank you for your patience as we work to improve our town's infrastructure!
Schedules are subject to change based on weather and unforeseen circumstances.