Please plan for the following schedule as we move into the weekend:
-
Thursday (7/9): No casting or paving work is scheduled.
-
Friday (7/10): Paving will begin on Old Summer Street and a large portion of Summer Street (from Main Street toward Milford Street). The same road closure used for yesterday's casting work will be back in place.
-
Saturday (7/11): The casting company will be on-site adjusting structures to prepare the roadway for next week.
-
Monday (7/13): There will be a major roadway shutdown on Summer Street to continue paving. Full details regarding detour routes and timing will be shared no later than Friday.