Water Main Project Update: Week of August 31, 2020
Brentwood area
Work will continue on Karen Ave and Carole Ln. Pending test results, houses may begin to be connected to the temporary bypass. Road closures will occur in the locations of excavation and be adjusted daily.
Holliston Street
Work will continue between Main St and Higgins Ln. with hydrant installations, side street connection, and house services. (The extent of work will depend on the schedule for filling the the new main and testing). The road will be closed Monday between Main St and Lovering St.