Posted on: August 20, 2024 - 8:32am
Crews will be paving Populatic Street today, Tuesday, August 20. Once Populatic St. is complete, crews will move on to Village St. and tackle any remaining work on Oakland St. and then Cassidy Lane.
The Cassidy Lane sidewalk has been loamed, but we have decided to hold off on the remaining paving until Friday (August 23) when we will be paving the Village St sidewalk. Sidewalk work will resume on Wednesday with demolition. All of this work should be wrapped up on Friday.
Cassidy Field's parking lot has been pulverized and rough graded. We will lay out pipes/grades today (8/20), and equipment will be brought in.
Lastly, some strategic painting will also take place at the Lovering St./Holliston St. intersection area, among other major road crossing striping.